View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7308
Project Title: CCTV System (NNCC - CCTV System)
Agency: NNCC
Division: NNCC
Department: NDOC
Project Manager: CAD
Description: Replace Cable TV equipment and cables.
Location: Carson City
DI_Location_2: 0
Project Description: This project would replace the existing cable in the institution with the new cable used by cable and satellite companies to get the reception required by the new televisions sold to the inmates. The cable at our institution has not been replaced or upgraded for many years. The reception in some units is very poor as additional power boosters need to be added due to the number of inmates housed in the unit.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Install CATV Cable (1,500 ea @ $250/ea) 375,000
2 Cable Equipment (30 ea @ $2,500/ea) 75,000
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 450,000