Application ID: 7304
Project Title: Tower #3 Sally Port and Office (Northern Nevada Correctional Center)
Agency: NNCC
Division: NNCC
Department: NDOC
Project Manager: RLC
Description: Upgrade the existing Sally Port at Tower 3 & create a new Sally Port at Unit 7A Intake with a 400 sf control station/office.
Location: Carson City
DI_Location_2: 0
Project Description: This project includes upgrading the sally port gates at Tower #3 and a 400 sf addition to the sally port office. Upgrades to the gates include replacing the gates with power operated gates interfaced with a sally port office, and new cameras that will assist with the automation of the sally port operations. The addition of the sally port office will house an employee workstation to monitor and control traffic in and out of the institution during the day.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition 10,000
2 AC Paving (3,400 sf @ $6.5/sf) 22,100
3 Upgrade Gates with Power Operators (2 ea @ $15,000/ea) 30,000
4 Power Operated Gates (2 ea @ $35,000/ea) 70,000
5 Security Fencing (100 lf @ $235/lf) 23,500
6 Control Station / Office (400 sf @ $400/sf) 160,000
7 Extend Utilities 85,000
8 Telecom & Cameras 55,000
9
10
11
12
13
14
15
16
Total 455,600