View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7303
Project Title: Doors, Locks & Controls (NNCC - Unit 7)
Agency: NNCC
Division: NNCC
Department: NDOC
Project Manager: CAD
Description: Replace locks, control panels, and distress buttons. Project also includes conversion from hinges to sliding doors.
Location: Carson City
DI_Location_2: 0
Project Description: This project is to replace hinged doors with sliding doors and replace door control and lock hardware in unit 7 at NNCC. This will include doors and slide mechanisms, locks, distress buttons, wiring, and control panels. The existing equipment is original to these units, and is at the end of its useful life. The plan is to phase the construction, working in one wing at a time.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace Panels, Locks, Buttons & Wiring (168 ea @ $6,500/ea) 1,092,000
2 Replace Hinged with Sliding Doors (168 ea @ $13,500/ea) 2,268,000
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 3,360,000