Application ID: 7300
Project Title: Housing Unit (Warm Springs Correctional Center)
Agency: WSCC
Division: WSCC
Department: NDOC
Project Manager: RLC
Description: Site adapt the design and construct a 52,760 sf Nevada "T" 168-Cell Housing Unit.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project will design and construct a Nevada "T" 168-Cell housing unit at the Warm Springs Correctional Center (WSCC). The location of the housing unit is proposed to be located to the east of the existing perimeter fencing. The project will also fund a master plan for an additional housing unit and other administration and core services facilities to meet the growing needs of WSCC. The furniture and equipment scope is for beds and day room tables.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Site Development (250,000 sf @ $8/sf) 2,000,000
2 Nevada "T" Housing Unit (52,760 ea @ $635/ea) 33,502,600
3 Guard Tower (2 ea @ $785,000/ea) 1,570,000
4 Extend Utilities 450,000
5 Security Fencing (1,600 ea @ $387.2/ea) 619,520
6 High Mast Lighting & Cameras 665,500
7
8
9
10
11
12
13
14
15
16
Total 38,807,620