View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7297
Project Title: Restroom Remodel & Fixture Replacement (Housing Units #1 & #2, Warm Springs Correctional Center)
Agency: WSCC
Division: WSCC
Department: NDOC
Project Manager: TJD
Description: Remodel existing restroom & shower areas and replace plumbing fixtures. Includes water control system replacement for plumbing fixtures.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of work for this project includes the renovation of the shower and restroom areas as well as the replacement of plumbing fixtures serving Housing Units #1 and #2. The project includes replacing existing flooring, wall/ceiling finishes, plumbing fixtures, water controls, piping, valves, and access panels/doors. Access to some of the plumbing chase areas is difficult because the access doors are too small. This project will increase the exterior access door sizes on Housing Unit #2.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Piping & Equipment 85,000
2 Piping, Valves, & Accessories 160,000
3 Stainless Steel Toilet Fixture (77 ea @ $2,300/ea) 177,100
4 Lavatory Fixture (77 ea @ $2,100/ea) 161,700
5 Stainless Steel Shower Fixture (16 ea @ $1,000/ea) 16,000
6 Toilet/Lavatory Combination Fixture (20 ea @ $2,600/ea) 52,000
7 Flush Valve (97 ea @ $175/ea) 16,975
8 Hot & Cold Water Valve (113 ea @ $150/ea) 16,950
9 Sensor Button Modifications (323 ea @ $60/ea) 19,380
10 Water Saving Controller (30 ea @ $250/ea) 7,500
11 Testing, Balancing, & Commissioning 10,000
12 Electrical Modifications 20,000
13 Interior Access Panel Modifications (20 ea @ $250/ea) 5,000
14 Exterior Access Door Modifications (30 ea @ $1,500/ea) 45,000
15 Restroom & Shower Renovation (1,500 sf @ $65/sf) 97,500
16
Total 890,105