View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7296
Project Title: Guard Tower (Warm Springs Correctional Center)
Agency: WSCC
Division: WSCC
Department: NDOC
Project Manager: JJD
Description: Add new Guard Tower to North side perimeter, including fencing.
Location: Carson City
DI_Location_2: 0
Project Description: Construct new Guard Tower based on Prison 8 design at the north side of the facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Guard Tower 785,000
2 Site Work / Pad Prep 25,000
3 Site Utilities 70,000
4 Security Fencing (225 lf @ $220/lf) 49,500
5
6
7
8
9
10
11
12
13
14
15
16
Total 929,500