View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7295
Project Title: Security Cameras Upgrade (TLVCC)
Agency: TLV
Division: TLV
Department: NDOC
Project Manager: CAD
Description: Install cameras, single viewing station and digital storage . This is for the Three Lakes Valley Conservation Camp.
Location: Indian Springs
DI_Location_2: 0
Project Description: TLVCC Security Surveillance camera system upgrade Project description (One Sentence): The Surveillance system is poor repair and rarely used. A modern DVR system intranet based for increased safety and security A modern surveillance system will improve safety and security to the operations at TLVCC. The current system is in poor condition and is not sustainable. A new intranet based system will allow custody staff to record, view in real time, and monitor a greater portion of the yard from their desk top.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Cameras Inside (50 ea @ $4,000/ea) 200,000
2 Cameras Outside (50 ea @ $5,000/ea) 250,000
3 Enhanced Digital Storage 75,000
4 Trenching, Conduit, Conductor Install (2,200 lf @ $50/lf) 110,000
5 Viewing Station (7 ea @ $2,500/ea) 17,500
6
7
8
9
10
11
12
13
14
15
16
Total 652,500