View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7293
Project Title: Planning Project for a Housing Unit (Southern Desert Correctional Center)
Agency: NDOC
Division: NDOC
Department: NDOC
Project Manager: JJD
Description: Planning Project for a Nevada "T " Housing Unit.
Location: Indian Springs
DI_Location_2: 0
Project Description: This planning project will get a "T" Style Housing Unit and modifications to the mechanical systems design completed and ready for construction. The new housing unit will be located inside the existing perimeter fence near the existing 240 bed dorms. Other infrastructure improvements will be fully designed. This project will utilize the same Prime Consultant (Architect) as project 07-P03 Prison 8 - Planning. Therefore, the state can utilize the existing design to optimize resources and also reduce A/E Design and Supervision fees.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Construct "T" Housing Unit (52,760 sf @ $520/sf) 27,435,200
2 Mechanical Upgrades 2,000,000
3 Site Improvements 775,000
4
5
6.
7.
8.
9.
10.
11
12
13
14
15
16
Total 30,210,200