View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7291
Project Title: Replace Security Glazing (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: JJD
Description: Replace Security Glazing at the central control of housing units 1,5,6,7 and Gatehouse/ Control
Location: Indian Springs
DI_Location_2: 0
Project Description: This project will replace the security glazing in four (4) of SDCC's Housing Units' Central Control Rooms and Gatehouse Secure Entry.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Housing Units Central Control Glazing @ 5 Sides (4 ea @ $30,000/ea) 120,000
2 Housing Units Central Control Cage @ 5 Sides (4 ea @ $30,000/ea) 120,000
3 Gatehouse Security Glazing (6 ea @ $6,000/ea) 36,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 276,000