Application ID: 7290
Project Title: Door Replacement - Units 1 5 6 & 7 (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: JJD
Description: Cell Door Replacement, Security Gates & Glazing Replacement - Units 1,5,6, 7
Location: Indian Springs
DI_Location_2: 0
Project Description: The project will replace the cell doors, locks, wing gates and security control room glazing for Housing Units 1, 5, 6 & 7. This will include the control room equipment. This will be similar to the door & lock replacement already accomplished in units 2, 3 & 4.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Buildings 1, 5, 6 - Replace Cell Doors (336 ea @ $2,500/ea) 840,000
2 Buildings 1, 5, 6 - Replace Locks (336 ea @ $2,200/ea) 739,200
3 Building 7 - Replace Locks (112 ea @ $2,200/ea) 246,400
4 Buildings 1, 5, 6, 7 - Replace Wing Gates (12 ea @ $60,000/ea) 720,000
5 Buildings 1, 5, 6, 7 - Replace Glazing in Bubble (4 ea @ $10,000/ea) 40,000
6 Buildings 1, 5, 6, 7 - Door Frames (448 ea @ $500/ea) 224,000
7 Buildings 1, 5, 6, 7 - Install Touch Screen Control Systems 1,500,000
8
9
10
11
12
13
14
15
16
Total 4,309,600