View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7287
Project Title: Gym Floor Replacement (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: JJD
Description: Gym Flooring Replacement
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of this project will replace failing basketball / gym sports court flooring and VCT in the remainder of the Southern desert Correctional Center Gym Building.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Multi-Use Floor Demolition (5,400 sf @ $5/sf) 27,000
2 Remainder of Building Floor Demo (13,000 sf @ $2/sf) 26,000
3 Basketball Court Subfloor Repair / Preparation (5,400 sf @ $5/sf) 27,000
4 Multi-Use Flooring (5,400 sf @ $18/sf) 97,200
5 Remainder of Building VCT Flooring (13,000 sf @ $5/sf) 65,000
6
7
8
9
10
11
12
13
14
15
16
Total 242,200