SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Stainless Steel Combination Units (240 ea @ $3,300/ea) 792,000
2 Demolition (240 ea @ $500/ea) 120,000
3 Plumbing Modifications 120,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 1,032,000