View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7278
Project Title: Install Perimeter Lighting (ECC)
Agency: ECC
Division: ECC
Department: NDOC
Project Manager: CAD
Description: Ely Conservation Camp Pole Lighting
Location: Ely
DI_Location_2: 0
Project Description: This request is for the installation of light poles including fixtures, controls, trenching, conduit, wiring and connections to existing utilities.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Poles with Lighting (20 ea @ $7,000/ea) 140,000
2 Conduit, Conductors, Trenching & Repairs (2,000 lf @ $50/lf) 100,000
3 Lighting Controls 10,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 250,000