View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7276
Project Title: Shower and Bathroom Renovations (Ely Conservation Camp)
Agency: ECC
Division: ECC
Department: NDOC
Project Manager: CSB
Description: Remove and replace showers and bathroom renovations at ECC
Location: Ely
DI_Location_2: 0
Project Description: The scope of this project is to renovate the shower and bathroom facilities by removing and replacing existing showers and assorted piping, refurbish existing shower surfaces by bead blasting grouted areas and resealing. In addition, remove existing floors and replace with epoxy flooring.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove & Replace Shower Valves (12 ea @ $1,500/ea) 18,000
2 Remove & Replace Assorted Piping 135,000
3 Steel Shower Partitions & Accessories (12 ea @ $6,500/ea) 78,000
4 Remove Floor Coating (2,304 sf @ $5/sf) 11,520
5 Level Floor (2,304 sf @ $10/sf) 23,040
6 Apply Epoxy Flooring (2,304 sf @ $25/sf) 57,600
7 Ceiling & Wall Finishes 25,000
8 Countertops, Sinks, Mirrors & Lighting 30,000
9
10
11
12
13
14
15
16
Total 378,160