Application ID: 7275
Project Title: Shower Replacement (Pioche Honor Camp)
Agency: PCC
Division: PCC
Department: NDOC
Project Manager: JJD
Description: Replace shower stalls with stainless steel shower stalls
Location: Pioche
DI_Location_2: 0
Project Description: This project will replace 36 shower stalls with stainless steel shower stalls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition (36 ea @ $1,500/ea) 54,000
2 Re-Work Existing Stud Walls & Gyp Bd (36 ea @ $1,000/ea) 36,000
3 Stainless Steel Shower Inserts (36 ea @ $13,000/ea) 468,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 558,000