Application ID: 7274
Project Title: Replace Liner and Enlarge Wastewater Ponds 1 & 2 (SDCC)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: BJW
Description: Replace the liners in Wastewater Ponds 1 & 2, and enlarge the ponds.
Location: Indian Springs
DI_Location_2: 0
Project Description: The project will provide design and construction for the removal and replacement of the liners in wastewater ponds 1 & 2 at the Southern Desert Correctional Center (SDCC). The project scope also includes enlarging the ponds from to provide additional capacity.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Sludge Removal & Disposal (10,000 cy @ $105/cy) 1,050,000
2 Divert Standing Liquid 150,000
3 Remove & Replace Pond Liner (375,000 sf @ $2.5/sf) 937,500
4 Subgrade Preparation (375,000 sf @ $.3/sf) 112,500
5 Excavation (100,000 cy @ $7/cy) 700,000
6
7
8
9
10
11
12
13
14
15
16
Total 2,950,000