View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7268
Project Title: Replace Perimeter Security Fence (Carlin Conservation Camp)
Agency: CCC
Division: CCC
Department: NDOC
Project Manager: BJW
Description: Replace existing 6' perimeter fence with a 10' perimeter fence with razor ribbon wire.
Location: Carlin
DI_Location_2: 0
Project Description: This project scope of work is construction of a new perimeter fence to replace an existing 6 foot fence at the Carlin Conservation Camp (CCC). The new fence will consist of a 10' high chain link perimeter fence with 36” of razor ribbon wire along the top, and associated access gates.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove Perimeter Security Fence (1,700 lf @ $5/lf) 8,500
2 Construct Perimeter Security Fence (1,700 lf @ $100/lf) 170,000
3 Install 20' Slide Gate 10,000
4 Install 20' Swing Gate (2 ea @ $7,500/ea) 15,000
5 Install 3' Swing Gate (4 ea @ $1,000/ea) 4,000
6
7
8
9
10
11
12
13
14
15
16
Total 207,500