Application ID: 7264
Project Title: Shower Improvements (Carlin Conservation Camp)
Agency: CCC
Division: CCC
Department: NDOC
Project Manager: RLC
Description: Installation of stainless shower enclosures in the housing units
Location: Carlin
DI_Location_2: 0
Project Description: This project includes the design and installation of 24 stainless steel shower enclosures at the existing shower units. The shower floors will also be replaced.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition 15,000
2 Wall Repairs & Preparation 24,000
3 Stainless Steel Enclosures (24 ea @ $19,260/ea) 462,240
4 Poured Shower Floors (480 sf @ $40/sf) 19,200
5 Shower Head & Controls (24 ea @ $850/ea) 20,400
6
7
8
9
10
11
12
13
14
15
16
Total 540,840