Description: Upgrading and modernization of the firing range
Location: Lovelock
DI_Location_2: 0
Project Description: This project includes the design and construction of major renovation to the Firing Range Facility. Improvements to this facility include re-grading the site to improve safe firing backgrounds, construction of a firing control office, restrooms, video surveillance, audio PA system and site lighting.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Utilities 65,000
2 Straight Away Shooting Range (40,000 sf @ $6.5/sf) 260,000
3 Short Range / Tactical (35,000 sf @ $10/sf) 350,000
4 Control House & Restrooms (600 ea @ $325/ea) 195,000
5 Benches & Shade Structures (2 ea @ $25,000/ea) 50,000
6 Lighting (5 ea @ $5,000/ea) 25,000
7
8
9
10
11
12
13
14
15
16
Total 945,000