View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7261
Project Title: Multipurpose Gymnasium Improvements (Carlin Conservation Camp)
Agency: CCC
Division: CCC
Department: NDOC
Project Manager: RLC
Description: Renovate the multipurpose gymnasium including an ADA restroom, replacement of building insulation, minor roof repairs and door replacements
Location: Carlin
DI_Location_2: 0
Project Description: This project includes the design and renovation of the Gymnasium. Improvements include conversion of the restroom to meet accessibility standards, replacement of two man doors, minor metal roofing repairs, repair/replacement of wall and ceiling insulation, and replacement of the gym's evaporative cooling unit.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remodel ADA Restroom 10,000
2 Site & Building Modifications for ADA Restroom Access 7,000
3 Replace Man Doors (2 ea @ $3,500/ea) 7,000
4 Roofing Repairs 5,000
5 Wall & Ceiling Insulation (5,618 sf @ $4/sf) 22,472
6 Evaporative Cooler 7,500
7
8
9
10
11
12
13
14
15
16
Total 58,972