Application ID: 7255
Project Title: Fire Sprinkler Installation (Wells Conservation Camp)
Agency: WCC
Division: WCC
Department: NDOC
Project Manager: KRS
Description: Fire sprinklers installation Housing unit and NDF facilities.
Location: Wells
DI_Location_2: 0
Project Description: The scope of this project is to install fire sprinklers in the housing unit and NDF buildings. Based on current calculations, the facility existing water storage tank of 130,000 gallons will meet fire fighting water capacity requirements for this facilit

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Fire Riser Installation (4 ea @ $9,000/ea) 36,000
2 Underground Trenching & Piping (450 lf @ $100/lf) 45,000
3 Fire Sprinkler Installation (23,824 sf @ $11/sf) 262,064
4 Fire Pump Servicing & Upgrades 50,000
5 Fire Monitoring & Connection to Existing System 4,000
6
7
8
9
10
11
12
13
14
15
16
Total 397,064