Application ID: 7254
Project Title: Replace Sanitary Sewer Lift Station (Pioche Conservation Camp)
Agency: PCC
Division: PCC
Department: NDOC
Project Manager: BJW
Description: Construct a duplex grinder lift station with electrical controls, underground wet well, inflow vault, and abandon existing lift station.
Location: Pioche
DI_Location_2: 0
Project Description: This project will design and construct a new sanitary sewer lift station and abandon the existing lift station at the Pioche Conservation Camp (PCC). An initial project study will also be conducted to determine whether the lift station can be eliminated and a gravity sewer line installed in-lieu. The proposed pump station will include a precast wet well, duplexed grinder pumps, electrical controls, and associated piping modifications.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Abandon Existing Lift Station 5,000
2 Install Grinder Lift Station with Controls 250,000
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 255,000