View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7244
Project Title: Electronic Card Access System (Grant Sawyer Office Building)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: CAD
Description: This will upgrade the controls to 150 doors and provide head-end and badging equipment.
Location: Las Vegas
DI_Location_2: 0
Project Description: Install new card access system and upgrade to the widely used operating system at the Grant Sawyer Office Building.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Replace Door Controls (150 ea @ $3,000/ea) 450,000
2 Badging Equipment 20,000
3 Head-End Equipment 30,000
4 Architectural Repairs (150 ea @ $450/ea) 67,500
5 Lock Replacement (150 ea @ $600/ea) 90,000
6 Replace Combiner Boxes (15 ea @ $8,000/ea) 120,000
7
8
9
10
11
12
13
14
15
16
Total 777,500