View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7237
Project Title: Upgrade Perimeter Security Fence (SCC)
Agency: SCC
Division: SCC
Department: NDOC
Project Manager: BJW
Description: Replace the existing 6' perimeter fence with a 10' perimeter fence with razor ribbon wire.
Location: Carson City
DI_Location_2: 0
Project Description: The project scope will design and construct a new perimeter security fence to replace an existing 6' high fence enclosing the Stewart Conservation Camp (SCC). The proposed fence will consist of a 10' high chain link perimeter fence with 36" of razor ribbon wire along the top, associated access gates, and keycard access control at two main gates. A secure facility allowance is included to allow installation of an electrical conduit through the facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remove Perimeter Security Fence (1,100 lf @ $5/lf) 5,500
2 Construct Perimeter Security Fence (1,100 lf @ $100/lf) 110,000
3 Install 20' Swing Gate (4 ea @ $7,500/ea) 30,000
4 Install 3' Swing Gate (2 ea @ $1,000/ea) 2,000
5 Install Gate Access Controls 25,000
6
7
8
9
10
11
12
13
14
15
16
Total 172,500