View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7236
Project Title: Roof Replacement, SCC Housing Units 1-5.
Agency: SCC
Division: SCC
Department: NDOC
Project Manager: AJL
Description: Replace Shingle Roofing System.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project is to remove and replace the shingled roofing system on SCC's Housing Units 1-5 in Carson City. The new shingled roofing will insure a water tight system.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Shingle Tear Off & Disposal (26,500 sf @ $1/sf) 26,500
2 Shingle Installation (26,500 sf @ $9/sf) 238,500
3 Misc Components (26,500 sf @ $.5/sf) 13,250
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14
15
16
Total 278,250