View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7235
Project Title: Evaporative Cooler Replacement (Housing Units #1 through #5, Stewart Conservation Camp)
Agency: SCC
Division: SCC
Department: NDOC
Project Manager: TJD
Description: Replace existing evaporative coolers, ductwork, piping, and controls.
Location: Carson City
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of the existing cooling systems serving the five (5) housing units at SCC. The project will include replacing the existing evaporative coolers, fill & drain piping, ductwork, and related controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Equipment & Ductwork 30,000
2 Evaporative Cooler (2,500 cfm) (15 ea @ $3,750/ea) 56,250
3 Evaporative Cooler Roof Curb Modifications (15 ea @ $3,000/ea) 45,000
4 Domestic Water & Drain Piping Modifications 20,000
5 Backflow Preventer Installation (5 ea @ $2,500/ea) 12,500
6 Air Distribution & Ductwork Modifications 10,000
7 Temperature Control System Modifications 30,000
8 Testing, Balancing, & Commissioning 25,000
9 Crane/Rigging 10,000
10 Electrical Modifications 30,000
11
12
13
14
15
16
Total 268,750