View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7232
Project Title: Heating System Renovation (TCC)
Agency: TCC
Division: TCC
Department: NDOC
Project Manager: BBM
Description: This project will renovate the heating water system at the Tonopah Conservation Camp.
Location: Tonopah
DI_Location_2: 0
Project Description: This project will replace the heating water boilers, domestic water heaters and baseboard heaters at the Tonopah Conservation Camp.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Condensing Boilers (500 mbh) (2 ea @ $25,000/ea) 50,000
2 Water Heater (100 mbh) 30,000
3 Water Heater (40 mbh) 15,000
4 Circulation Pumps 15,000
5 Baseboard Heaters 170,000
6 Piping Modifications 35,000
7 Plumbing Modifications 8,000
8 Demolition 9,000
9 Electrical 4,000
10 Temperature Controls 14,000
11 Testing & Balancing 2,500
12 Commissioning 1,000
13
14
15
16
Total 353,500