View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7231
Project Title: Showers Restrooms & Culinary Remodel (Tonopah Honor Camp)
Agency: TCC
Division: TCC
Department: NDOC
Project Manager: JJD
Description: Replace showers, restrooms & culinary flooring to comply with current ADA, Health Safety and Building Codes.
Location: Tonopah
DI_Location_2: 0
Project Description: This project will replace the showers, restroom fixtures as well as remove and replace the restroom and culinary flooring.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Shower Demolition (24 ea @ $1,500/ea) 36,000
2 Re-Work Existing Stud Walls & Gyp Bd (24 ea @ $1,000/ea) 24,000
3 Shower - Stainless Steel Inserts (24 ea @ $13,000/ea) 312,000
4 Restroom Fixture Replacement 214,005
5 Restroom Flooring Demolition (2,250 sf @ $5/sf) 11,250
6 Restroom Flooring (2,250 sf @ $18/sf) 40,500
7 Culinary Flooring - Equipment Move / Storage (1,300 sf @ $2/sf) 2,600
8 Culinary Flooring - Demolition (1,300 sf @ $5/sf) 6,500
9 Culinary Flooring - Quarry Tile Replacement (1,300 sf @ $35/sf) 45,500
10 Temporary Kitchen - Rental 30,000
11 Temporary Kitchen - Utilities to Trailer 5,500
12 Temporary Kitchen - Propane Rental 30,000
13.
14
15
16
Total 757,855