SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7230
Project Title: Advance Planning - Renovation and Seismic Retrofit (Heroes Memorial Building & Annex)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: RMO
Description: Programming through schematic design, including seismic analysis, for an existing 20,741 sf building
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project is to complete the programming and schematic design for seismic strengthening and a major remodel of the Heroes Memorial Building and Annex. This proposed project would provide significant upgrades to the structure, building systems, and provide more effective use of available spaces. In addition, the Programming study will address planning options for the relocation of staff that will be displaced during the rehabilitation of the buildings. Heroes Memorial and the Annex are historic buildings, located on the Capitol Complex, and are part of the Attorney General’s office building complex. Funding for the completion of the construction documents and construction would be requested in the 2019 legislative session.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Building Construction (21,000 sf @ $450/sf) 9,450,000
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 9,450,000