View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7229
Project Title: Demolition of Cottages (Northern Nevada Childrens Home)
Agency: SPWD
Division: SPWD
Department: Admin
Project Manager: KRS
Description: Demolition of 6 Cottages and Limited Restoration
Location: Carson City
DI_Location_2: 0
Project Description: The scope of this project is to demolish the six cottages at the Northern Nevada Children's Home facility. This project does not include the historic gym or the administrative offices located on the site. The administrative facilities and historic gym will remain for potential future renovation.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Asbestos Abatement (15,890 sf @ $5/sf) 79,450
2 Utility Abandonment (15,890 sf @ $2.5/sf) 39,725
3 Building Demolition (15,890 sf @ $8/sf) 127,120
4 Landscaping (15,890 ea @ $1.5/ea) 23,835
5
6
7
8
9
10
11
12
13
14
15
16
Total 270,130