Description: Make repairs to Jacobsen Ave., Wa Pai Shone Ave., Crescent Dr. and Gibson Ave. at theStewart Complex.
Location: Stewart
DI_Location_2: 0
Project Description: This project will perform necessary rehabilitation and maintenance on Jacobsen, Gibson and Wa Pai Shone Avenues at the Stewart Complex.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Cutting & Patching (18,000 sf @ $5/sf) 90,000
2 Asphalt Crack Repair (1,000 lf @ $4/lf) 4,000
3 Crack Seal (165,000 sf @ $.1/sf) 16,500
4 Microsurfacing (165,000 sf @ $.75/sf) 123,750
5 R&R Crescent Drive 65,000
6.
7.
8.
9
10
11
12
13
14
15
16
Total 299,250