View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7216
Project Title: Preventative Pavement Maintenance (Decatur DMV)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: CSB
Description: Crack seal, slurry & re-stripe the asphalt pavement at the Decatur DMV
Location: N. Las Vegas
DI_Location_2: 0
Project Description: This project will provide cleaning, crack seal, slurry seal and re-striping of the asphalt pavement at the existing Decatur DMV facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Clean & Crack Seal (255,430 sf @ $.1/sf) 25,543
2 Cleaning & Type '2' Slurry Seal (255,430 sf @ $.45/sf) 114,944
3 Parking Striping (433 ea @ $12/ea) 5,196
4 ADA Striping (15 ea @ $35/ea) 525
5 Miscellaneous 5,000
6
7
8
9
10
11
12
13
14
15
16
Total 151,208