View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7213
Project Title: ADA Entry & Restroom Remodel (Stewart Building 18)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: MCR
Description: Remodel restroom into unisex ADA restrooom, install ADA signage and exterior conrete
Location: Stewart
DI_Location_2: 0
Project Description: This Project will conduct ADA retrofits to the interior and exterior of Building 18 at the Stewart Complex. The interior work will remodel the restroom and install interior signage and the exterior work will include removing and replacing sidewalks, restr

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Remodel Existing Restroom Into Uni-Sex Restroom 18,000
2 Install ADA Signage (3 ea @ $350/ea) 1,050
3 Replace Concrete (1,000 sf @ $12/sf) 12,000
4 Restriping (200 lf @ $1/lf) 200
5 Exterior Signs (2 ea @ $350/ea) 700
6.
7.
8.
9.
10.
11.
12
13
14
15
16
Total 31,950