View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7212
Project Title: ADA Upgrades Nevada State Library & Archives
Agency: LibArch
Division: LibArch
Department: Admin
Project Manager: MCR
Description: Remodel restrooms, add accessible drinking fountains and add signage to the Nevada State Library & Archives
Location: Carson City
DI_Location_2: 0
Project Description: This Project will conduct ADA retrofits to the interior of the Nevada State Library. Upgrades will occur in the bathrooms, remove and replace drinking fountains, install casework and add cane detection at stairs. The above work will comply with the Americ

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Upgrade Restrooms (5 ea @ $5,000/ea) 25,000
2 Extend Existing Cabinetry (3 lf @ $975/lf) 2,925
3 Install 3 Hi/Low Drinking Fountains (3 ea @ $4,000/ea) 12,000
4 Cane Sweep Detection for Stairs 2,950
5 Install Signage (10 ea @ $350/ea) 3,500
6
7
8
9
10
11
12
13
14
15
16
Total 46,375