View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7208
Project Title: Site Drainage Improvements (Attorney General's Office Complex)
Agency: B&G
Division: SPWD
Department: Admin
Project Manager: BJW
Description: Construct a storm drain system on the east side of the Attorney General Offices Complex to improve site drainage.
Location: Carson City
DI_Location_2: 0
Project Description: Project scope will provide design and construction for site drainage improvements on the east side of the Attorney General's Office and Heroes Memorial Building within the Attorney General's Office Complex. The project scope includes abandonment of existing infiltrations drains, installation of a new storm drain system, removal and replacement of concrete sidewalk, and connection of two building drains into storm drain piping.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Sidewalk Removal & Replacement (2,500 sf @ $30/sf) 75,000
2 Site Grading (1,000 sf @ $5/sf) 5,000
3 Abandon Existing Infiltration Drain (3 ea @ $2,000/ea) 6,000
4 Trench Drain (50 lf @ $160/lf) 8,000
5 Storm Drain (300 lf @ $130/lf) 39,000
6 Storm Drain Cleanout (5 ea @ $1,500/ea) 7,500
7 Connect to Existing Catch Basin 2,500
8 Connect Roof Drain to Storm Drain (2 ea @ $2,500/ea) 5,000
9
10
11
12
13
14
15
16
Total 148,000