SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Boiler Burner Assemblies (7 ea @ $100,000/ea) 700,000
2 Control Modifications (7 ea @ $50,000/ea) 350,000
3 Commissioning 40,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 1,090,000