View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7193
Project Title: Air Handler Replacement - Activity Building (High Desert State Prison)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: BBM
Description: This project will replace the eight air handling units that serve the Activity Building at the High Desert State Prison.
Location: Indian Springs
DI_Location_2: 0
Project Description: This project will replace the air handling unit serving each activity room for Housing Units 1 through 8 at the High Desert State Prison.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Air Handling Units (10,000 cfm) (8 ea @ $110,000/ea) 880,000
2 Ductwork/Air Distribution 80,000
3 Piping Modifications 60,000
4 Temperature Controls 70,000
5 Chemical Treatment 8,000
6 Demolition/Rigging 15,000
7 Electrical 20,000
8 Roofing 14,000
9 Testing & Balancing 16,000
10 Commissioning 12,000
11
12
13
14
15
16
Total 1,175,000