Application ID: 7192
Project Title: Exterior Finishes Phase II (High Desert State Prison)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: JJD
Description: Exterior Finishes Phase II - Housing Units 9, 10, 11 12 and Prison Industries Building
Location: Indian Springs
DI_Location_2: 0
Project Description: This rehab effort includes expansion joints, control joints, caulking around window and door frames, re-paint all the exterior metal doors and window frames. This is Phase 2. Phase 1 was completed in the 2015 CIP.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Surface & Parapet Painting & Caulking (206,000 sf @ $7/sf) 1,442,000
2.
3.
4.
5.
6.
7.
8.
9.
10.
11
12
13
14
15
16
Total 1,442,000