Application ID: 7191
Project Title: Evaporative Cooler Media Replacement (High Desert State Prison)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: BBM
Description: This project will replace the evaporative cooler media for the rooftop air handling units installed in Phases I and II at the High Desert State Prison.
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of this project is to replace the evaporative media in the air handling units installed in Phases I and II at the High Desert State Prison.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Evaporative Media (30,000 cfm) (3 ea @ $5,000/ea) 15,000
2 Evaporative Media (20,000 cfm) (46 ea @ $4,500/ea) 207,000
3 Evaporative Media (15,000 cfm) 4,000
4 Evaporative Media (10,000 cfm) (10 ea @ $3,500/ea) 35,000
5 Evaporative Media (7,500 cfm) (8 ea @ $3,000/ea) 24,000
6 Evaporative Media (4,000 cfm) (3 ea @ $2,500/ea) 7,500
7 Water Treatment (71 ea @ $500/ea) 35,500
8 Commissioning 2,000
9
10
11
12
13
14
15
16
Total 330,000