Application ID: 7187
Project Title: Solar Hot Water System Installation (Department of Corrections, Various Sites)
Agency: NDOC
Division: NDOC
Department: NDOC
Project Manager: TJD
Description: Installation of solar hot water collectors, tanks, pumps, piping, and controls.
Location: Various
DI_Location_2: 0
Project Description: The scope of work for this project includes the installation of solar hot water heating systems at various conservation camps. The project includes installing solar collectors, storage tanks, piping, pumps, and controls.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Equipment & Piping 20,000
2 Tonopah Conservation Camp Solar Water Heating System 60,000
3 Wells Conservation Camp Solar Water Heating System 60,000
4 Carlin Conservation Camp Solar Water Heating System 60,000
5 Humboldt Conservation Camp Solar Water Heating System 60,000
6 Ely Conservation Camp Solar Water Heating System 60,000
7 Pioche Conservation Camp Solar Water Heating System 60,000
8 Piping, Valves, & Accessories 130,000
9 Testing, Balancing, & Commissioning 65,000
10 Temperature Control Modifications 150,000
11 Electrical Modifications 30,000
12 Crane/Rigging 10,000
13
14
15
16
Total 765,000