View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7180d
Project Title: Plumbing Fixture Water Control Renovations (Housing Units 5 through 7 at SDCC)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: TJD
Description: Replace existing fixtures, piping, valves, and water saving control system.
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of plumbing fixture water controls serving Housing Units 5 through 7 at the Southern Desert Correctional Center. The project includes replacing existing water controls, piping, and valves. This same scope of work for the remaining housing units is planned to be requested in the 2019 CIP.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Piping & Equipment 45,000
2 Piping, Valves, & Accessories 172,500
3 Flush Valves (306 ea @ $225/ea) 68,850
4 Hot & Cold Water Valves (378 ea @ $200/ea) 75,600
5 Shower Head Replacement (36 ea @ $125/ea) 4,500
6 Sensor Button Modifications (990 ea @ $80/ea) 79,200
7 Water Saving Controllers (195 ea @ $325/ea) 63,375
8 Testing, Balancing, & Commissioning 30,000
9 Electrical Modifications 130,000
10
11
12
13
14
15
16
Total 669,025