View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7180c
Project Title: Plumbing Fixture & Water Control Renovations (Housing Units #1 through #4, Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: TJD
Description: Replace existing fixtures, piping, valves, and water saving control system.
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of plumbing fixtures and fixture water controls serving Housing Units #1 through #4 at Southern Desert Correctional Center. The project includes replacing existing plumbing fixtures, water controls, piping, and valves. The remaining housing units are planned to be completed in the 2019 CIP.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Piping & Equipment 210,000
2 Piping, Valves, & Accessories 245,000
3 Stainless Steel Toilet Fixture (408 ea @ $2,000/ea) 816,000
4 Stainless Steel Lavatory Fixture (408 ea @ $1,800/ea) 734,400
5 Stainless Steel Shower Fixture (48 ea @ $7,500/ea) 360,000
6 Flush Valve (408 ea @ $175/ea) 71,400
7 Hot & Cold Water Valve (456 ea @ $150/ea) 68,400
8 Sensor Button Modifications (1,463 ea @ $60/ea) 87,780
9 Water Saving Controller (258 ea @ $250/ea) 64,500
10 Testing, Balancing, & Commissioning 40,000
11 Electrical Modifications 130,000
12.
13
14
15
16
Total 2,827,480