Project Title: Plumbing Fixture & Water Control Renovations (Housing Units #1 through #12, High Desert Correctional Center)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: TJD
Description: Replace existing fixtures, piping, valves, and water saving control system.
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of plumbing fixtures and fixture water controls serving Housing Units #1 through #12 at High Desert Correctional Center. The project will replace existing plumbing fixtures, water controls, piping, and valves.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Piping & Equipment 400,000
2 Piping, Valves, & Accessories 880,000
3 Toilet/Lavatory Combination Fixture (688 ea @ $2,300/ea) 1,582,400
4 Stainless Steel Shower Fixture (48 ea @ $7,500/ea) 360,000
5 Flush Valve (2,048 ea @ $175/ea) 358,400
6 Hot & Cold Water Valve (2,288 ea @ $150/ea) 343,200
7 Sensor Button Modifications (6,624 ea @ $60/ea) 397,440
8 Water Saving Controller (1,184 ea @ $250/ea) 296,000
9 Testing, Balancing, & Commissioning 120,000
10 Electrical Modifications 600,000
11
12
13
14
15
16
Total 5,337,440