View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7180a
Project Title: Plumbing Fixture & Water Control Renovations (Housing Units #1 through #6, Lovelock Correctional Center)
Agency: LCC
Division: LCC
Department: NDOC
Project Manager: TJD
Description: Replace existing fixtures, piping, valves, and water saving control system.
Location: Lovelock
DI_Location_2: 0
Project Description: The scope of work for this project includes the replacement of plumbing fixtures and fixture water controls serving Housing Units #1 through #6 at Lovelock Correctional Center. The project includes replacing existing plumbing fixtures, water controls, piping, and valves.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Demolition of Existing Piping & Equipment 390,000
2 Piping, Valves, & Accessories 540,000
3 Toilet/Lavatory Combination Fixture (856 ea @ $2,300/ea) 1,968,800
4 Stainless Steel Shower Fixture (72 ea @ $7,500/ea) 540,000
5 Flush Valve (856 ea @ $175/ea) 149,800
6 Hot & Cold Water Valve (916 ea @ $150/ea) 137,400
7 Sensor Button Modifications (2,712 ea @ $60/ea) 162,720
8 Water Saving Controller (250 ea @ $250/ea) 62,500
9 Testing, Balancing, & Commissioning 60,000
10 Electrical Modifications 125,000
11
12
13
14
15
16
Total 4,136,220