View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7168
Project Title: HVAC and Kitchen Renovation (Jean Conservation Camp)
Agency: JCC
Division: JCC
Department: NDOC
Project Manager: BBM
Description: This project will renovate the HVAC systems and replace kitchen equipment at the Jean Conservation Camp.
Location: Jean
DI_Location_2: 0
Project Description: This project will replace the HVAC units and miscellaneous kitchen equipment at the Jean Conservation Camp.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Evaporative Cooler (5000 cfm) 4,200
2 Evaporative Cooler (3000 cfm) (5 ea @ $2,100/ea) 10,500
3 Evaporative Cooler (2000 cfm) (3 ea @ $1,650/ea) 4,950
4 Ductwork Modifications 22,500
5 Exhaust Fans (6 ea @ $12,000/ea) 72,000
6 Walk in Oven 34,500
7 Cooktops (3 ea @ $12,500/ea) 37,500
8 Steam Tables (2 ea @ $17,500/ea) 35,000
9 Roofing 8,000
10 Demolition/Rigging 10,000
11 Electrical 15,000
12 Commissioning 2,000
13 Temperature Controls 4,000
14 Testing & Balancing 3,000
15 Water Treatment 4,500
16
Total 267,650