Application ID: 7167
Project Title: Install Water Tank Bypass Valves & Water Meter Lovelock Correctional Center
Agency: LCC
Division: LCC
Department: NDOC
Project Manager: BJW
Description: Install a water tank bypass line and new water meter.
Location: Lovelock
DI_Location_2: 0
Project Description: This project will design and construct, a bypass line, associated valves, water meter assembly, and vault at the Lovelock Correctional Center (LCC).

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Install 6" Bypass Water Line (200 lf @ $75/lf) 15,000
2 Install Gate Valves (4 ea @ $1,500/ea) 6,000
3 Perform Hot Tap Installation 5,000
4 Install Water Meter, Vault & Associated Piping & Valves 15,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 41,000