View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7166
Project Title: Evaporative Cooler Media Replacement (High Desert State Prison)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: BBM
Description: This project will replace the evaporative cooler media for the rooftop air handling units installed in Phases IV and V at the High Desert State Prison.
Location: Indian Springs
DI_Location_2: 0
Project Description: This project will replace the evaporative media in the air handling units installed in Phases IV and V at the High Desert State Prison.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Evaporative Media (15,000 cfm) (24 ea @ $4,000/ea) 96,000
2 Water Treatment (24 ea @ $500/ea) 12,000
3 Commissioning 5,000
4
5
6
7
8
9
10
11
12
13
14
15
16
Total 113,000