View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7163
Project Title: Install Perimeter Shaker Fence (High Desert State Prison)
Agency: HDSP
Division: HDSP
Department: NDOC
Project Manager: BJW
Description: Install a perimeter shaker fence with cameras inside of the existing perimeter fence.
Location: Indian Springs
DI_Location_2: 0
Project Description: This project will design and construct a new perimeter shaker fence system including new fence line security cameras and associated site electrical upgrades at the High Desert State Prison (HDSP).

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Install Shaker Fence (9,100 lf @ $125/lf) 1,137,500
2 Install Camera System (100 ea @ $4,000/ea) 400,000
3 Install Security Electronics & Monitors 150,000
4 Install Electrical Service (9,100 lf @ $50/lf) 455,000
5
6
7
8
9
10
11
12
13
14
15
16
Total 2,142,500