View Recomended 2019 CIP Data

SPWD Project Managers have compiled the following data from previous CIP Application Subbmittals. Please review the data, if any adjustments need to be made please contact SPWD.


Application ID: 7161
Project Title: Security Cameras (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: CAD
Description: Install cameras, workstations and digital storage .
Location: Indian Springs
DI_Location_2: 0
Project Description: Install 300 cameras in all housing units, yards, and common areas of the original correctional facility. Install monitoring at each control area.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Fixed Cameras (260 ea @ $4,000/ea) 1,040,000
2 Pan-Tilt-Zoom Cameras (40 ea @ $5,000/ea) 200,000
3 Enhanced Digital Storage 200,000
4 Trenching, Conduit, Conductor Install (8,000 lf @ $50/lf) 400,000
5 Install 25 Workstations (25 ea @ $2,500/ea) 62,500
6
7
8
9
10
11
12
13
14
15
16
Total 1,902,500