Application ID: 7160
Project Title: Admin & Gatehouse Expansion (Southern Desert Correctional Center)
Agency: SDCC
Division: SDCC
Department: NDOC
Project Manager: JJD
Description: Expand the Administration Building & Gatehouse
Location: Indian Springs
DI_Location_2: 0
Project Description: The scope of this project will expand the existing entry gate house adding visitor seating, restrooms and two separate entrances. Two separate entrances, one for visitors and one for the staff, ensures adequate space for the gate house officer to properly inspect the visitors and for the staff easier access to the facility.

SPWD Construction Cost Estimate from June 2016


Line Item Cost
1 Gatehouse Addition (2,000 sf @ $575/sf) 1,150,000
2 Closed Circuit Monitor & Camera (3 ea @ $6,000/ea) 18,000
3 Public Address System 10,000
4 Site Demolition & Pad Preparation (2,500 sf @ $15/sf) 37,500
5 Security Scanning Equipment 30,000
6
7
8
9
10
11
12
13
14
15
16
Total 1,245,500